Click here to open a PDF version of this tip sheet
WHEN IS A PERMIT TRANSFER REQUIRED?
This Tip Sheet provides instructions on how to transfer a permit between owners or contractors when changes need to be made to the permitholder on an active permit. This may be required in cases of sale or new ownership, change in contractor, or court awarded property receivership.
REQUIREMENTS TO TRANSFER AN ISSUED PERMIT:
The following statements are required to transfer an issued permit from one party’s name into a different party’s name:
- Written statement from the current permit holder releasing permit responsibility and authorizing transfer to the new permit holder
- Written statement from the new permit holder accepting permit responsibility
- Payment of Permit Transfer fee – This fee will be invoiced once we receive notice of the transfer
Please Note: If the transfer involves a change of property owner, and the approved drawings are marked as “for the original owner’s use ONLY”, the design professional will need to give written permission for the new owner to use the drawings.
CONTRACTOR REQUIREMENTS
If the permit is getting transferred to a contractor, that contractor must meet all the standard requirements:
- Active state contractor’s license
- Active Tacoma business license
- Active right-of-way bond on file with our department, if applicable to the scope
TO INITIATE A PERMIT TRANSFER
Send an email to permits@tacoma.gov requesting a permit transfer, and list all applicable permit numbers for the project. For the purposes of permit transfers, written statements are accepted via email.
See Page 2 for additional requirements for Work Order and Major Level 2 SDEV Permits.
REQUIREMENTS TO TRANSFER AN ACTIVE PERMIT, PRIOR TO ISSUANCE:
The following statements are required to transfer an active, unissued permit from one party’s name into a different party’s name:
- Written statement from the current permit applicant releasing permit responsibility and authorizing transfer to the new permit primary contact/applicant
- Also, for any formally produced plan sets, the design professional must give written permission for the new owner/applicant to use the drawings
- Written statement from the new permit holder accepting permit responsibility
- No transfer fee is required when the permit has not yet been issued
EXCEPTIONS
- No transfer fee is required to change general contact information on the permit that is unrelated to the current permitholder. Current applicant approval will be requested in order to to add any new contact without a history of connection to the permit.
- If the property owner is also the applicant, they can authorize changes to the permit in writing (e.g. swapping out contractors) without needing a written statement from the current permit holder.
WORK ORDERS & MAJOR LEVEL 2 SDEVS:
In addition to the written statements and permit transfer fees outlined in the previous section, the following will be required prior to transfer of Work Orders and Major Level 2 Site Development Permits:
ADDITIONAL REQUIREMENTS TO TRANSFER:
ISSUED WO OR ML2 SDEV PERMIT
- Written statement from the Engineer of Record-acknowledging that they will be supporting any future field changes, record drawings and engineered certifications
- If construction has started and the engineer of record will be changing, a Commercial Field Revision is required. Please upload the new plan set, stamped for approval by the new engineer of record, consistent with WAC196-23-020.
- Any proposed changes to the original stamped drawings must also be thoroughly reviewed and stamped by a licensed engineer accepting liability for those changes.
- Completed Financially Responsible Party Agreement Form
- Right of Way Bonded Contractor information
- Payment of any permit balance
- A Preconstruction meeting may be required post-issuance if no work has occurred and both contractor and owner are changing from the original meeting.
PLEASE NOTE, for projects requiring a Performance Bond – Any existing performance bonding in place will not be released until valid replacement bonding has been received from the new project owner/financially responsible party.
WO OR ML2 SDEV PERMIT, PRIOR TO ISSUANCE
- Written statement from the Engineer of Record-acknowledging that they will be supporting any future field changes, record drawings and engineered certifications
- If the existing Engineer of Record will not sign off, a new permit submittal will be required.
- Completed Financially Responsible Party Agreement form
- Payment of any permit balance
- The new applicant/contractor will be required to attend a Pre-Review meeting before any subsequent reviews and a Preconstruction Meeting prior to issuance.
ADDITIONAL RESOURCES:
Preconstruction Meeting
Commercial Site Development
Work Order Permits
Field Revisions
Financially Responsible Party Form