Click here to open a PDF version of this tip sheet
What are System Development Charges (SDC)?
System Development Charges (SDC) are one-time fees charged to new development and redevelopment projects and designed to share the capital costs of public water, wastewater and stormwater utilities. These fees enable development to proportionately share the cost of expanding capacity of these utilities rather than shifting these costs to all ratepayers.
What types of SDCs does Tacoma have?
Tacoma has three SDCs, one for each water-based utility:
| Utility | Administered By | Status |
| Wastewater | Environmental Services | Effective July 1, 2026 |
| Stormwater | Environmental Services | Effective July 1, 2026 |
| Water | Tacoma Water | In place since 1997 |
What type of project pays SDCs?
An SDC is due when a project or development connects to Tacoma’s Wastewater, Stormwater, or Water utility for the first time, or when a project or development increases its capacity needs relative to one of these utilities:
|
Wastewater |
For any project that (1) connects to the wastewater system for the first time, (2) upsizes to a larger water meter, or (3) adds more residential units to a parcel or parcels. |
|
Stormwater |
For any project that increases the amount of impervious surface (non-porous hard surface) on a parcel or parcels. |
|
Water |
For any project that (1) connects to this utility for the first time, (2) upsizes to a larger water meter, (3) adds residential units to a parcel or parcels, (4) converts a dedicated fire service to a service for use other than exclusively fire protection, or (5) requires additional flow beyond what had previously been purchased. |
How much will my SDC cost?
|
Wastewater |
Varies depending on the size of the new water meter being installed, whether the development is residential or commercial, the number of residential units being added, and whether residential units are separately metered or connect to a shared water meter. |
|
|
Stormwater |
$0.53 per square foot of added impervious surface. |
View Fee Schedule and Ordinance |
|
Water |
Varies depending on the size of the new water meter to be installed or upgraded, whether the meter is to serve a residential, commercial, or irrigation function, the number of residential units to be served by the meter, or, in the case of meters larger than 2”, the anticipated average day and peak day flow volumes. |
|
When are SDC payments due?
| Wastewater | Before receiving the building Certificate of Occupancy |
| Stormwater | Before issuance of the project’s site development permit |
| Water | Before water meter installation or, in the case of meters larger than 2”, when usage is greater than 110% of previously anticipated usage during a 12-month period. |
Are there exemptions, waivers, or subsidies available for SDCs?
The city is currently evaluating potential waivers or subsidies for qualifying affordable housing. The results of this evaluation will be presented to City Council in Q3 2026.